Construction Process of Anti-Crack Grid
01
Existing Packaging Surface Layering

· Inject new joint materials for joints and cracks on existing road surfaces
· Repair cross-section if necessary

02
Road cleaning

· Remove foreign substances such as oil on the road to increase the adhesion of the reinforcement materials
· Cleaning of solvents, water, compressed air
· Spray Bitumen after cleaning

03
IAN GEOTEC Anti-Crack Grid (Civil Fiber) Construction

· Attach to prevent wrinkles
· 1 to 2 times of compaction with tire roller

04
Overlay Post-Post-Post pledge

· Lay asphalt at the allowable temperature on the day of installation of the anti-crack grid
· Maintains thickness of 40 mm or more